We hope you are keeping well during these challenging times. We would like to take this opportunity to provide you with an update regarding the Camden Goods Yard regeneration project.

We have now received the final consent needed to allow some initial enabling works on site commencing Tuesday 14th April 2020. These works are minor in nature and are projected to take place over the next four weeks and will include:

  • Site establishment including a perimeter hoarding and welfare facilities
  • Canopy removal works
  • Removal of the forecourt surface
  • Removal of the fuel tanks
  • Trial hole works
  • Removal of the kiosk

Our project website is the best way to stay in touch with our progress. You can view all the latest news and sign up for our regular updates at www.camdengoodsyardconsultation.com.

We will also be rescheduling our Construction Working Group session and will be in touch with a date for this next week.

Thank you for your understanding and patience during this time. If you have any questions or concerns, please do not hesitate to contact our team by emailing feedback@camdengoodsyard.com or call 0800 298 7040.

Kind regards,

Nick Hazzard
Senior Construction Manager,
St George