Concrete Power Float Works (June – July 2023)
Concrete Power Float Works
Please see the attached letter regarding concrete power float works at Camden Goods Yard
Power Floating Works – Potential Extended Working Hours
Please see the attached letter regarding potential out of hours works at Camden Goods Yard
View our Community Newsletter Update (July 2022)
Sign up for regular updates
We will keep you informed of our progress, any community or consultation events and ways to get involved.
Latest news
Update on construction work for the marketing suite at Camden Goods Yard
Camden Council have approved plans for some limited out of hours works at Camden Goods Yard, as per the information below: The fit out works will be internal only and not disturb residents. The works will take place until 6th March 2024 at the following times: Monday...
Upcoming Weekend Works – Changeover of Power Supply
Dear Neighbour, We write to inform you that there will be work taking place this Saturday 4th and Sunday 5th November between 8am and 6pm. An electrical engineer contractor will be working within the Camden Goods Yard site this Saturday and Sunday. The contractors...
Upcoming Weekend Works – Tower Crane Dismantling (Update)
Dear Neighbour, Further to our email on Friday 1st September regarding the weekend works to dismantle Tower Crane 3A and Tower Crane 4 within the Camden Goods Yard main site. We are writing to remind you of the upcoming dates of weekend work. There will be extended...
Upcoming Weekend Works – Tower Crane Dismantling
Dear Neighbour, We are writing to update you on the upcoming dismantling of Tower Crane 3A and Tower Crane 4 within the Camden Goods Yard main site. There will be extended hours required on the Saturday and Sunday of each week to complete this work. We have permission...
Cadent Works Update
Dear Neighbour, We are writing to inform you about works that are due to be undertaken by Cadent. Cadent will start their work on Monday 10th July 2023, the work will last for 4 weeks. The work will be during site working hours 8am-6pm: Monday to Friday and Saturday...
Concrete Power Float Works (June and July Update)
Dear Neighbour, We wanted to keep you informed of the next set of dates for the month ahead, these will be: Day Date Friday 16th June 2023 Tuesday 20th June 2023 Wednesday 21st June 2023 Friday 23rd June 2023 Tuesday 27th June 2023 Wednesday 28th June 2023 Friday...
Virgin Media Diversion Works
Dear Neighbour, Virgin Media are due to undertake work that will take place between the railway bridge and the main existing entrance gate to Juniper Crescent. This will involve the diversion of a section of Virgin Media communications. Virgin Media’s contractor Kelly...
Concrete Power Floating Work Update (March 2023)
Dear Neighbour, We updated you on Friday 10th February 2023 to inform you about the concrete pouring work that would be carried out this month on the Camden Goods Yard (CGY) main site in the basement levels. The power floating work, which is already underway, will...
Concrete Power Float Works (February 2023)
Dear Neighbour, We are writing to let you know of upcoming planned works on the Camden Goods Yard (CGY) main site which relate to the concrete pouring works in the basement. These may require some working outside of our standard permitted site hours. Power floating is...
UKPN works in the area
Dear Neighbour, We have been informed that UKPN will be undertaking some works this weekend to remove plant from their substation on the Morrisons site and to reconnect some cables located underneath the footpath on Stephen Street, on the Juniper Crescent side. This...